J.J. Pickle – Austin, TX
Remedial Roofing & Waterproofing
Contract Amount: $1,400,000 (approx.)
Owner: GSA
Architect: Jacobs
General Contractor: Hensel Phelps
Scope of Work: Modified bitumen roofing system, exterior precast restoration, cut out and re-caulk, perimeter window sealant replacement, granite injection, precast injection
Project Description: Re-roof for a Level IV federal facility
Greystar TMC Residential – Houston, TX
New Construction Roofing & Waterproofing
Contract Amount: $2,200,000 (approx.)
Owner: Medistar and Greystar – A joint venture
Architect: Preston Partnership
General Contractor: Hoar Construction
Scope of Work: Crystalline waterproofing, hot fluid-applied asphalt waterproofing, bentonite waterproofing, fluid-applied waterproofing, site sealants, traffic coating, insulation, air barrier, joint sealants, caulking, sheet metal, thermoplastic membrane roofing, coping, scuppers, counter flashing, downspouts
Project Description: 35-story luxury high-rise
Travis County Medical Examiner’s Office Building – Austin, TX
New Construction Roofing
Contract Amount: $650,000 (approx.)
Owner: Travis County
Architect: BGK Architects
General Contractor: Harvey Cleary
Scope of Work: Hot asphalt roofing system, built-up roofing system, standing seam roofing system
Project Description: Two-story office building
US 281 North Via Park and Ride – San Antonio, TX
New Construction Waterproofing
Contract Amount: $300,000 (approx.)
Owner: Via
Architect: RVK
General Contractor: Sundt
Scope of Work: Expansion joints, traffic coating, joint sealants, air barrier
Project Description: Four-story park and ride parking garage
Kinsmen Lutheran Church – Houston, TX
Remedial Roofing & Waterproofing
Contract Amount: $400,000 (approx.)
Owner: Kinsmen Lutheran Church
Consultant: BES Terracon
General Contractor: Chamberlin Roofing & Waterproofing</br />
Scope of Work: PVC membrane roofing system, shingles, wall and curb flashings, sheet metal, elastomeric coating
Project Description: Church renovation
IAH Terminal D Baggage Claim – Houston, TX
Remedial Waterproofing
Contract Amount: $200,000 (approx.)
Owner: Houston Airport Systems
Architect: Pierce Goodwin Alexander & Linville
General Contractor: Manhattan Construction
Scope of Work: Shot blasting, traffic coating
Project Description: Renovation of baggage claim
Gables Uptown Trail – Dallas, TX
Remedial Waterproofing
Contract Amount: $850,000 (approx.)
Owner: Gables Residential Services, Inc.
Architect: WJE
General Contractor: Chamberlin Roofing & Waterproofing
Scope of Work: Waterblasting, joint sealants, expansion control, cement plastering, painting and coating
Project Description: Residential community
CityLine Block D – Richardson, TX
New Construction Roofing & Waterproofing
Contract Amount: $700,000 (approx.)
Owner: City of Richardson
Architect: Wallace Garcia Wilson Architects
General Contractor: JLB Builders, LLC
Scope of Work: Fluid-applied waterproofing, joint sealants, firestopping, site and paving sealants, TPO roofing, flashing and sheet metal
Project Description: Multi-family community
Coffee Creek Water Resource Recovery Facility – Edmund, OK
New Construction Waterproofing
Contract Amount: $100,000 (approx.)
Owner: Coffee Creek Water RRF
Architect: BBN Architects
General Contractor: Lambert Construction
Scope of Work: Hot fluid-applied rubberized asphalt waterproofing, water repellents, air barrier, joint sealants, site and paving sealants
Project Description: Wastewater facility expansion
Texas A&M Galveston Academic Building – Galveston, TX
New Construction Roofing & Waterproofing
Contract Amount: $1,000,000 (approx.)
Owner: Texas A&M University
Architect: PGAL
General Contractor: Linbeck Group
Scope of Work: Fluid-applied waterproofing, hot fluid rubberized asphalt waterproofing, weather barrier, sheet metal flashing, site sealants, modified bitumen roofing, TPO roofing, standing seam roofing, joint sealants and traffic coating
Project Description: