During the summer of 2012, significant wear and tear issues on the 45 year-old building became apparent and needed to be addressed. This high-rise structure, complete with elongated concrete shade devices made of clad with granite panels, began to experience pieces of the exterior falling from the building causing major concern for pedestrians below. Overhead protection was immediately installed around the building to protect passersby. Chamberlin was asked by the consultant, Wiss, Jan
Getting Ready for Game Day
At the conclusion of the exterior survey, it was recommended that the damaged concrete precast panels be repaired. In August of 2012, Chamberlin was asked to immediately begin concrete repairs to the north side of the building. The challenge was the team had to be complete before September 1st, which meant exterior cleaning would need to be finished at another time. Damaged concrete was removed down to the rebar and repaired. The sidewalk and street on the north side of the building is used for tailgating during the Longhorn football season and scaffolding was required to be down in time for the first home game. As a result of the extremely tight schedule, adjustm
“Foreman, Jeff Dittrich and Superintendent, Dave Edwards, worked extremely hard and long hours to make sure Chamberlin finished the work on time,” said Patrick Halaszyn, Chamberlin Operations Manager. “The tight timeline was the biggest challenge and they executed it very well.”
When it was time for Longhorn tailgating, work moved to the sout
Once football season was over, Chamberlin returned to the north side of the building to complete the work which included wet glazing all windows and the removal and replacement of all joint sealants. Over 100,000 linear feet of sealants were replaced by Chamberlin crews over the life of the project.
Work Access Area
The unique structure of the building made some areas of work difficult to reach. To help with this task, four swing stages were utilized with special b
“Edwards, Dittrich and the Chamberlin crew were great to work with. They knew how to overcome challenging conditions and responded quickly to any issues,” said Keith Simon, Associate III, with WJE. “Safety is taken seriously with Chamberlin and that is very much appreciated.”
Time was not necessarily on Chamberlin’s side during the work on the LBJ State Office Building, but having a committed team made the difference in meeting the tight deadline.
“We enjoy doing work with Chamberlin and hope to continue working with them in the future,” said Simon.